Based on a reliable and affordable supply of LNG, the solution will allow the Bécancour TransCanada Energy (TCE) plant to become a strategic tool for meeting the growing electricity needs of Quebecers during very cold spells.
Winter/Spring 2016 |
BAPE public hearings and consultation process (as needed). Preliminary engineering. |
Fall 2016/Winter 2017 |
Order issued following the environmental assessment process. Detail engineering. |
Spring 2017 |
Start of construction. |
December 2019 | Commissioning. |
32% ↓ of GHGs
99% ↓ of SO2 emissions
70% ↓ of NOx emissions
70% ↓ of fine particulates
To register your company in our database, please complete the form
Bécancour, July 8, 2015
Site de stockage et de regazéification de GNL à Bécancour - Du gaz naturel accessible et économique pour répondre aux besoins électriques de pointe (PDF)Press release - Énergir Solutions Énergie dresse un bilan positif de sa séance d'information (PDF)
Bécancour, September 23, 2015
Site de stockage et de regazéification de GNL à Bécancour - Présentation des résultats de l'analyse d'impact sur l'environnement (PDF)
Site de stockage et de regazéification de GNL à Bécancour - Sommaire des résultats de l’étude d’impact sur l’environnement (PDF)
Press release - Une deuxième séance d'information et de consultation pour Énergir Solutions Énergie (PDF)
Bécancour, April 13, 2016
Site de stockage et de regazéification de GNL à Bécancour - Séance d'information du BAPE (PDF)
Need more information?
Contact us!
By phone at 1 800 361-4568 or by email.